A practical week-by-week timeline for launching a private label under-eye patch — from manufacturer shortlisting to first shipment.
Ninety days sounds short for a brand-new skincare SKU. It's actually a reasonable window for a private label under-eye patch if you run sourcing, formulation, compliance, and packaging in parallel instead of sequentially. This is the timeline we use with first-time brand founders who want to be production-ready before their marketing window.
Weeks 1–2: brief and shortlist
Write a one-page brief covering target skin concern, hero ingredients, claims you want to make, and — crucially — the markets you will sell into. Markets drive compliance, and compliance drives which factories can actually help you. Shortlist three manufacturers that:
- hold ISO 22716 or equivalent GMP
- have references in your target market
- can commit to a sampling window in writing
Weeks 3–4: sampling and hero formula lock
Expect two rounds of samples.
- Round one validates the texture and delivery format (hydrogel vs. microneedle).
- Round two tightens the active-ingredient dosing and packaging fit.
Demand stability data summaries with each round — not the full accelerated-aging report, but a confirmation that the base formula has cleared stability at 40°C / 75% RH.
Weeks 5–6: compliance dossier in parallel
Do not wait for final formula sign-off to start compliance. Your manufacturer should be assembling the Product Information File, ingredient disclosures, and country-specific documents as soon as the hero formula is locked.
| Market | What you need |
|---|---|
| EU | CPNP notification + Responsible Person |
| US | FDA facility registration + Drug Facts box if OTC |
| UK | SCPN notification + UK Responsible Person |
| GCC | Halal certificate + Arabic labelling |
Weeks 7–9: packaging, artwork, pilot batch
Packaging is where launch timelines most commonly slip. Two rules keep you on track:
- Use stock primary packaging (tray + lidding film) for the first production run. Bespoke tooling can wait until you have real sell-through data.
- Lock artwork two weeks before the pilot batch. Pilot batches exist to catch physical defects, not to re-spec your font choices.
Weeks 10–12: production, QA, first shipment
At this point you should receive a Certificate of Analysis tied to the production lot number, an MSDS, and — if shipping by sea — fumigation and commercial-invoice documents matching the lot. Store these alongside the PIF. When a marketplace audit happens two months after launch, this paper trail is the difference between a 24-hour response and a delisting.
What actually goes wrong
Most 90-day launches we see slip for one of three reasons:
- Artwork revisions after the plate is already on press
- Stability data not being handed over with samples
- The brand discovering late that the market they planned to launch in requires documents their manufacturer was not asked to prepare
All three are preventable with a written dossier checklist on day one. Talk to our launch team and we'll send you the exact template we use with new brand founders.
Planning a launch like this?
Our team can scope sampling, compliance, and packaging in a single reply. Typical response time is one business day.
Get in touch